Major Irrigation Canals


1.Main Ravi Canal

  • SALIENT FEATURES
  • Project Overview

    Year of Start: 1974-75
    Year of Completion:1981-82
    Design Discharge of Canal: 1150 Cusecs
    Total Length of Main Ravi Canal: 79.8 Kms
    Total Number of Distributaries: 20 Nos.
    Total Length of Distribution Network: 420 Km

    Pumping Stations

    A) Basantpur

    Installed Capacity: 5+1 (standby) of 100 Cusecs each

    Actual Present Discharge: 200 Cusecs

    B) Lakhanpur

    Installed Capacity: 12+3 (standby) of 17 Cusecs each

    Actual Present Discharge: 68 Cusecs

    Other Features
    • Number of Villages Covered: 140
    • Culturable Command Area (CCA):32,186 Ha
    • Ultimate Irrigation Potential: 54,072 Ha
    • Irrigation Potential Utilized:23,904 Ha
    Balance Portion of Ravi Canal

    The balance portion of the Ravi Canal, which spans 1.37 Km from the reservoir to the existing canal at Basantpur, is being constructed by the ShahPur Kandi Dam Authority as per the agreement signed between the Government of Jammu & Kashmir and Punjab. Almost 90% of the work has been completed, and it is expected to be fully completed by June 2024.

    Project for Modernization of Ravi Canal

    A project worth ₹571.83 Crore has been framed to restore and modernize the Main Ravi Canal and its distributary network. The goal is to carry a discharge of 1150 Cusec, which will be available after the commissioning of the ShahPur Kandi Dam. The benefit-cost ratio of the project is 2.40, signifying its high potential for positive returns and long-term sustainability.

2.Main Tawi Canal

  • SALIENT FEATURES
  • Feature Details
    Year of Commissioning 1973
    Design Discharge of Canal 300 Cusecs
    Total length of Main Canal 28.40 Kms
    Total no. of Distributaries 11 No.s
    Total length of Distribution network 180 Km
    No. of Pumps 5+1 (standby)
    Installed Capacity 60 cusecs each
    Actual Present Discharge 200 cusecs
    No. of Villages 30
    Culturalable Command Area (CCA) 12560 Ha
    Discharge of each Pump 60 Cusecs
    Ultimate Irrigation Potential 21480 Ha
    Irrigation Potential Utilised 13000 Ha
    Subsidiary Lift Scheme Raya

    Discharge: 36 Cusecs, CCA: 1500 Acres (Rabi only), Pumps: 5x7.2 Cusecs + 1 standby